Current DPW Projects

Lincoln Street Pavement Operations

  • Contractor: Nocella Landscaping and Construction
  • Project: Milling and paving of Lincoln Street - full width and from School St to Summer St. Road only not sidewalks at this time.
  • Timeline: Starting Thursday 8/16/18 through Friday 8/24/18, weather permitting 7am-4pm each weekday - no work on the weekend.
  • Information: Travel along Lincoln, to the schools and driveways permitted during construction. Detours and one-way alternating traffic as needed. No parking on either side during construction hours. Police detail on site. During construction there will be raised castings, please drive carefully and slowly.

Lincoln Street Bridge Repairs

  • Contractor: NEL Corp
  • Project: Lincoln Street Bridge Repair
  • Timeline: Starting week of 7/9/18
  • Information: Work will continue on 8/8/18 through the day and from 2:00 pm through the early evening on Thursday 8/9/18. Detours in place, police detail on site.

Central Street Test Boring Work - COMPLETE 

  • Contractor: New England Boring
  • Project: Central Street bridge replacement design preparation work
  • Timeline: Starting Tuesday August 7, 2018   8:00am - 4:30 pm through the week, weather permitting
  • Information: One way alternating traffic and no parking signs as needed, police detail on site, 

Pump Stations

  • Contractor: Weston & Sampson
  • Project: Replacement of sewer pumps and installation of back-up power at the pumping stations on Ashland Ave, Rockwood Heights, Pine St and Old Essex Rd
  • Timeline: Starting mid July 2018 - Old Essex Rd
  • Information: pump station work underway, this should not impact residents, except for minor traffic flow interruptions. 

Please see the Archive DPW Projects page to reference completed projects